Grouting should not take place until after the specified curing period provided by the EOR.
Prior to grouting the PS=Ø couplers or joint, verify all of the materials have arrived on-site. Confirm condition of grout, size of joint, and usage of PS=Ø Closure Strip. Check the couplers for debris and water. Please be sure to review ACI Hot/Cold Weather Concrete Procedures.
Our grout has a working temperature range of 45° F to 90° F, avoid grout from freezing overnight. Grout has a shelf life of 12 months from date of manufacture, store in a cool, dry, indoor environment.
If you have any questions during this process, please contact our team as we are happy to assist.
Verify inventory and condition of the following items.
1.SIKAGROUT 885MF
2.Mixing Bucket
3.Slump Sheet
4.Slump Tube
5.Mixing Paddle
6.Funnel or Grout Pump
1. Mix Grout.
Follow mixing instructions on Grout Bag. Utilize required amount of water per bag of grout. Small batches are recommended as grout has a 30-minute working time and cannot be retempered.
2. Check Slump
Mix Grout for a minimum of 5 minutes. Then check slump utilizing provided slump tube and slump chart. 6” is recommended for couplers, 8” is recommended for joint.
3. Grout Couplers
Grout couplers first. Filling one grout tube completely until grout comes out opposite grout tube.
4. Grout Joint
Grout joint. Ensure grout is filling the entire depth of the slab. Utilize a trowel to get a flush finish as needed.
Tab Content